The gangway and the first slip are in position at the Marina, and we hope to start construction of the main arm within the next few weeks. They will count with water, electricity, cable TV and telephone lines upon completion. We
are ready in allocating slips. Interested, please contact us at: The work on the new Nautipesca building at the Marina is over 90% finished. This building was constructed upon request due to the fact that the previous site at the Cruise Ship Terminal Building became too small for the demand. We hope they can move soon and open the door to the public, and wish them success in their new house Construction of the Mini Market and Deli to offer services right from the marina is underway. The two sections of the new dock by the Terminal are finished. These docks will be used by the cruise ship tenders to disembark passengers as programmed. [ Close window ] |
|